This page contains the latest information on construction activities on site, with key completed works to date and “Look Ahead” works. The newsletters are available to download in the “Documents” section of this website.
Look Ahead
Works Completed to Date
First phase of piling works are complete.
First phase of jacking works are complete.
New delivery gate installation.
76% of Nuffield House piling is complete.
95% of Pegasus House probing is complete.
90% of the B1 slab is now removed.
Obstruction removal completed.
Temporary works installations are ongoing to allow excavations to commence.
Adaptions to propping along Piccadilly elevation completed.
Works commenced to breakout existing foundations allowing new pile caps to be installed in Nuffield House.
Nuffield House mini piling is complete.
Pegasus House probing and UXO survey completed.
B2 thrust block completed.
Lower waler beam installation complete.
2nd phase of underpinning along Sackville Street is 80% complete.
Nuffield House pile cap formations and removal of existing foundations continued.
Perimeter façade access scaffold continued.
Pegasus House piling is 25% complete.
Construction of guide wall for piling in Pegasus House.
12 Week Look Ahead
12 Week Look Ahead
Substructure works continue.
Pile mat installation.
Pegasus House piling continues.
Pile cap formations continue in Nuffield House, including the removal of existing foundations.
2nd Phase of underpinning along Sackville Street will complete.
Temporary work installations continue.
Excavating / reducing level in Pegasus House for temporary works and piling.
Façade access scaffold installation continues (including new Haki staircase and site entrance turnstile on corner of Sackville Street).
Construction of guide wall for piling in Pegasus House.
Formation of L Block loading bay adjacent to 36 Sackville Street.