This page contains the latest information on construction activities on site, with key completed works to date and “Look Ahead” works. The newsletters are available to download in the “Documents” section of this website.
Look Ahead
Works Completed to Date
Removal of temporary works continued including the green façade retention steelwork.
Perimeter scaffold continued.
Concrete works were practically completed.
Façade works and window installation continued on the Sackville Street and Albany elevations.
Façade clean first visit complete.
Mansard roof steel works commenced.
Feature staircase primary steelwork commenced.
Brick and blockwork continued.
Fitout works progressed including screeding, MEP, drylining and decorating.
12 Week Look Ahead
Removal of temporary works and façade retention steelwork will continue.
Perimeter scaffold will continue.
Concrete works will complete & Keltbray to decant from site.
Façade works and window installation will progress to all levels.
Façade clean will continue.
Mansard roof steelwork to complete.
Waterproofing to level 7 slab will be completed.
Feature staircase primary steelwork install will continue.
Brick and blockwork will continue throughout all floors.
Fitout works including screeding, MEP, drylining and decorating will continue.