This page contains the latest information on construction activities on site, with key completed works to date and “Look Ahead” works. The newsletters are available to download in the “Documents” section of this website.
Look Ahead
Works Completed to Date
Pegasus House pile cap formations completed.
Manhole and drainage construction continued.
Vent tunnel works completed.
Trimming of Albany Court wall protrusions completed.
Poured basement (Level -2).
Continued the removal of temporary works.
Continued columns and liner wall concrete pours.
Slipform operation complete and rig dismantled.
Sackville Street gantry removed.
Basement slab pours completed.
Additional welfare cabins installed.
12 Week Look Ahead
Temporary works removal will continue.
Liner wall works will be completed.
Ground floor slab will be completed.
Level 1 post tensioned slabs will commence.
Blockwork will commence.
Mechanical and electrical plant deliveries to commence.
Façade works to commence.
Thames water works to commence in Sackville Street (by others).